Before the build: give each unfinished choice a decision date
Work backwards from when the team needs the answer.
How to prepare outstanding home-building decisions with the right information, realistic deadlines and a clear distinction between a preference and an instruction.
Before building starts, I would ask for a conversation about the choices still open. It is tempting to work through them room by room, starting with whatever feels most exciting. I would instead ask which answer the team needs first. A fitting installed late in the job may need attention much earlier if someone must draw, price or order it before other work can proceed.
Key points
- Ask for decision dates that include time for checking, pricing and ordering.
- Describe the exact answer needed, rather than leaving a broad item such as bathroom selections on the list.
- Keep a preferred option separate from permission to order or build.
Ask what needs to happen before the delivery
Start with the builder's programme and ask the team to work backwards for each unresolved selection. When is it needed on site? When would the order need to be placed? What must the designer, supplier or installer confirm before that order can be made?
BRANZ's Level guidance identifies availability and long delivery lead-in times as considerations when choosing materials. That does not give you a reliable delivery date for your own order. Ask the supplier to confirm current availability for the exact product, quantity and finish, and ask when that information should be checked again.
- Allow time to obtain and understand a sample.
- Include any drawings or measurements needed before ordering.
- Agree who will tell you if the required decision date changes.
The process overview provides a starting point for discussing which choices belong in design development and which remain ahead of construction.
See how design decisions progress through the projectReplace a vague choice with a complete question
Consider a hypothetical bathroom where the owners want a wall-mounted basin tap but have only chosen its colour. I would ask the designer and plumber what information they need about the proposed tap, basin and vanity together. The useful decision might be an agreed arrangement with identified products, rather than a photograph of a finish.
Ask what you need to see to make that choice confidently. It could be a sample, a marked drawing or a comparison of two suitable options. If the question is still too broad to answer, give someone the task of preparing it. Writing 'client to decide' beside an unexplained item does not make it ready for a decision.
- What precisely am I choosing?
- What information is missing?
- Who will prepare that information, and when can we discuss it?
Separate liking it from releasing it
I would use plain descriptions of progress: being explored, preferred, checked and ready for an agreed instruction. You might prefer the tap before the team has checked its fit or confirmed its price. Make that distinction explicit when you send your answer.
Ask who is authorised to place the order and what confirmation they need. If a selection differs from the consented information, ask the designer to check the consent implications before anyone treats it as a simple swap. MBIE warns that changes to consented plans, including specified materials, can affect costs, timing and final sign-off.
The service describes support with proposed changes and design queries, with responsibilities agreed for the project.
Discuss architectural support for construction decisionsPrepare the next few decisions together
For a practical exercise, choose three outstanding selections and take them to a meeting. For each, write the answer needed, the missing information, who will supply it and the date by which you need to decide. Ask the team to check those dates against the work that follows. Arrange your showroom visits or household discussions around that sequence.
Leave space for questions that cannot be settled yet. If a measurement depends on work being completed, ask what can be prepared now and when the final check will happen.
Hayley's published renovation feedback mentions clear responses to builders' site queries. Questions will still arise during a build; preparing decisions means giving those questions a sensible route to an answer. If you have a start date approaching and a list of unresolved choices, bring both to a conversation. I would be happy to help you work out what needs attention first.
Her account describes the handling of site queries during her renovation, rather than promising a question-free build.
Read Hayley's renovation feedbackSources and further reading
Source information checked 7 November 2026 at 9:28 am GMT+13. Rules may change; check the linked official guidance for your project.
- Choosing materials | Level: Checked 7 November 2026; updated 30 January 2026. Supports checking availability and allowing for delivery lead-in times. No product-specific timeframe is claimed.
- Stages of the building process | Building Performance: Checked 7 November 2026; updated 9 September 2026. Supports the caution about changing consented plans and specified materials.
- Our Architectural Design Process | Modal Architecture: Checked 7 November 2026 for the contextual process link.
- Construction Support | Modal Architecture: Checked 7 November 2026 for support with design queries and proposed changes.
- Hayley Review | Modal Architecture: Review dated 9 August 2024; checked 7 November 2026. Attributed feedback about responses to builders' site queries.
Bring the question to your own project.
If this has helped you identify something you would like to explore, let’s talk about it.