How to compare builders’ estimates without getting lost in the totals
Find out what is making the numbers different.
A practical guide to comparing builders’ estimates, checking allowances and exclusions, and asking useful questions before choosing your build team.
You have two builders’ estimates for the same home and the totals are miles apart. It is tempting to pick the lower figure or assume the higher one is more thorough. I would hold off on both conclusions. My first question would be: where, exactly, do these two builders see the job differently?
Key points
- Check whether you are comparing estimates or quotes, and ask what each price is based on.
- Separate actual price differences from differences in the work, products and allowances included.
- Ask each builder to confirm clarifications in writing before using the comparison to make a decision.
Find out what kind of number you have
Consumer Protection explains that an estimate is an indication of likely cost rather than a fixed price. A quote offers specified work at a stated price. Ask the builder to explain the basis of their offer and the circumstances in which the amount could change.
I would also ask what decision the number is intended to support. Are we testing whether the developing design looks affordable, or choosing a contractor for a documented job? That distinction helps everyone avoid treating an early conversation as the final price.
- What information was used to prepare this price?
- Is it an estimate or a quote?
- How long is the offer valid, and what assumptions depend on the proposed start date?
Check the information before checking the arithmetic
Ask each builder to identify the drawing revisions, specifications and site information they priced. MBIE recommends providing detailed information and checking that offers cover the same work, materials and fixtures.
I would keep a short record of anything discussed after the documents were issued. Perhaps you mentioned a different kitchen layout during a site visit. Has that idea found its way into one price but not the other? Resolve the intended design with your team, then send the same clarification to everyone still pricing.
Modal Architecture's process explains the role of pricing reviews and scope clarification before construction.
See our tender and procurement stageGive allowances their own conversation
An allowance needs a little unpacking. MBIE describes a provisional sum as money allowed for work that cannot yet be priced firmly. A prime cost sum allows for an item you will select, and does not include installation unless stated.
Ask what product or work each allowance could realistically cover. A smaller allowance may reflect a different selection rather than a better price for your preferred one.
- Which items are allowances rather than settled prices?
- What selection or further information would allow them to be confirmed?
- Where are installation, GST and any applicable margins accounted for?
Try the kitchen comparison
Here is a hypothetical example. One builder has included cabinetry, a benchtop and installation. Another has allowed for cabinetry but expects you to organise the benchtop separately. Both have written 'kitchen' beside their figure.
I would ask both to describe the same finished kitchen, then confirm how their prices respond. Keep their original figures intact and put the clarification beside them. Do not quietly add your own guess to one total and present it as the builder's revised offer.
- Choose one area where the estimates differ.
- Write a plain description of what you expect to receive.
- Ask each builder to confirm inclusions, exclusions and any revised amount.
- Leave unanswered points marked as unresolved.
Bring the design team into the difficult gaps
If a price relies on an alternative product or a change to the design, I would ask the design team to review that suggestion before accepting it. Give them the actual proposal so the conversation stays specific.
Daniel from Warwick Gair Builders comments on the clarity of Modal Architecture's drawings and specifications in his published feedback. That is a useful aspect to explore when discussing your own project: how will design information reach the people pricing and building it?
This builder's review describes his experience using the practice's drawings and specifications.
Read Daniel's feedback on documentationFor an existing home, use the service overview to discuss the design work needed before seeking comparable prices.
Explore renovation and extension designFinish with a decision you can explain
I would want to explain why I preferred a builder after the outstanding questions were answered. Price matters, alongside relevant experience, references and confidence in how we will work together.
If you are planning a residential project and are unsure what information to have ready for pricing, bring that question to an initial conversation with Modal Architecture. We can discuss the next useful step.
Arrange an initial conversation about your plans and the support you may need before approaching builders.
Discuss your project and pricing preparationSources and further reading
Source information checked 11 October 2026 at 9:33 am GMT+13. Rules may change; check the linked official guidance for your project.
- Quotes and estimates | Consumer Protection: Checked 11 October 2026. Explains estimates and quotes, written detail and considerations beyond price.
- Tenders and quotes | Building Performance: Updated 17 April 2024; checked 11 October 2026. Explains pricing information, scope comparisons, provisional sums and prime cost sums.
Bring the question to your own project.
If this has helped you identify something you would like to explore, let’s talk about it.
Start a consultation